Key Milestone Achieved! 兗礦魯南化工凈化水廠提標改造項目 6KV 開關(guān)站一次受電成功
Good News!
Recently, the newly built 6KV switching station of the water purification plant upgrade project undertaken by CNCEC-TCC for Yankuang Lunan Chemicals Co., Ltd., successfully achieved its first energization. This milestone marks the official commissioning of the project’s power supply system, laying a solid foundation for subsequent debugging of wastewater treatment facilities, equipment trial runs, and the realization of the mechanical completion target by the end of 2025.
近日,由中國化學天辰公司總承包的兗礦魯南化工有限公司凈化水廠提標改造項目新建6KV開關(guān)站一次受電成功。這一關(guān)鍵節(jié)點的達成,標志著項目電力保障系統(tǒng)正式投入運行,為后續(xù)污水處理裝置調(diào)試、設(shè)備試運行及2025年底機械竣工目標的實現(xiàn)奠定了堅實基礎(chǔ)。

6KV開關(guān)站為三層建筑結(jié)構(gòu),建筑面積673平方米,自開挖換填至成功受電,歷時僅65天。為保障節(jié)點,天辰公司協(xié)同參建各方有序高效地推進工作,堅持日清日結(jié)且驗收合格。此外,全長約1500米的供電外線采用全程定向鉆拉管穿越方式,沿小儀河途經(jīng)村莊、農(nóng)田、河流及各類橋涵設(shè)施。工程通過精準定位實現(xiàn)了對周邊設(shè)施、植被和農(nóng)田的零傷害,從方案設(shè)計到施工全過程均展現(xiàn)出央企的環(huán)保責任與擔當。
此次成功受電,不僅彰顯了天辰公司項目團隊過硬的技術(shù)實力與精益管理水平,更為后續(xù)工作贏得了寶貴時間。項目團隊將以此為契機,乘勢而上推進后續(xù)工程,嚴把質(zhì)量關(guān)、安全關(guān)、進度關(guān),多措并舉保障項目高質(zhì)量如期完成,為業(yè)主和公司交上一份滿意答卷。